Building Production Stages

     
0     Permit Received Date  
  Start Process  
     
1     Dig 17 June 2004
Pour Footer 19 June 2004
Stock Block 21 June 2004
     
2     Block 22 June 2004
  Water/Damp Proofing 24 June 2004
  Brace Foundation 02 July 2004
  Drain Tiles 02 July 2004
  Foundation Inspection 06 July 2004
  Backfill 06 July 2004
     
3     Underground Plumbing 09 July 2004
Underground Inspection 12 July 2004
Pour Basement Floor/Slab 13 August 2004
Utility Laterals 24 July 2004
     
4     1st Floor Deck and Walls 13 July 2004
  2nd Floor Deck and Walls 13 July 2004
  Pour Garage Floor 12 July 2004
  Trusses 14 July 2004
  Tubs 30 July 2004
     
5     Sheathing 14 July 2004
Shingles 09 August 2004
Windows 16 July 2004
Rough HVAC 08 August 2004
     
6     Rough Plumbing 20 August 2004
  Rough Electric 20 August 2004
  Rough CBus 20 August 2004
  Exterior Paint 09 August 2004
     
7     Screw Wall Plates 04 September 2004
Mechanical Inspections 10 September 2004
Frame Inspection 14 September 2004
Insulation Installed 16 September 2004
Siding 15 September 2004
     
8     Insulation Inspection 21 September 2004
  Stock Drywall 22 September 2004
  Hang Drywall 23 September 2004
  Tape and Bed Drywall 23 September 2004
     
9     Skim Drywall 29 September 2004
Stipple Drywall 29 September 2004
Sand Drywall 29 September 2004
Sand Floors 29 September 2004
1st Trim 02 October 2004
Cut Drives/Walks 16 September 2004
     
10    Prime 7 October 2004
  Vinyl 7 October 2004
  2nd Trim 9 October 2004
  Pour Drives/Walks 23 September 2004
     
11     Final Plumbing 12 October 2004
Final HVAC 12 October 2004
Asphalt Drive 7 October 2004
Final Grade 7 October 2004
Gutters 30 September 2004
     
12     Final Electric 14 October 2004
  Final CBus 14 October 2004
  Drywall Punch 15 October 2004
  Conductors 12 October 2004
     
13    2nd Roll 19 October 2004
Mechanical Inspections 20 October 2004
Tractor Sod Grade
Sod/Seed/Landscape
     
14    Carpet 19 October 2004
  Clean  
  Final Paint  
  Certificate of Occupancy  
  Punchout  
  QUALITY WALK  
     
15    PreSettlement Inspections