Building Production Stages |
||
0 | Permit Received Date | |
Start Process | ||
1 | Dig | 17 June 2004 |
Pour Footer | 19 June 2004 | |
Stock Block | 21 June 2004 | |
2 | Block | 22 June 2004 |
Water/Damp Proofing | 24 June 2004 | |
Brace Foundation | 02 July 2004 | |
Drain Tiles | 02 July 2004 | |
Foundation Inspection | 06 July 2004 | |
Backfill | 06 July 2004 | |
3 | Underground Plumbing | 09 July 2004 |
Underground Inspection | 12 July 2004 | |
Pour Basement Floor/Slab | 13 August 2004 | |
Utility Laterals | 24 July 2004 | |
4 | 1st Floor Deck and Walls | 13 July 2004 |
2nd Floor Deck and Walls | 13 July 2004 | |
Pour Garage Floor | 12 July 2004 | |
Trusses | 14 July 2004 | |
Tubs | 30 July 2004 | |
5 | Sheathing | 14 July 2004 |
Shingles | 09 August 2004 | |
Windows | 16 July 2004 | |
Rough HVAC | 08 August 2004 | |
6 | Rough Plumbing | 20 August 2004 |
Rough Electric | 20 August 2004 | |
Rough CBus | 20 August 2004 | |
Exterior Paint | 09 August 2004 | |
7 | Screw Wall Plates | 04 September 2004 |
Mechanical Inspections | 10 September 2004 | |
Frame Inspection | 14 September 2004 | |
Insulation Installed | 16 September 2004 | |
Siding | 15 September 2004 | |
8 | Insulation Inspection | 21 September 2004 |
Stock Drywall | 22 September 2004 | |
Hang Drywall | 23 September 2004 | |
Tape and Bed Drywall | 23 September 2004 | |
9 | Skim Drywall | 29 September 2004 |
Stipple Drywall | 29 September 2004 | |
Sand Drywall | 29 September 2004 | |
Sand Floors | 29 September 2004 | |
1st Trim | 02 October 2004 | |
Cut Drives/Walks | 16 September 2004 | |
10 | Prime | 7 October 2004 |
Vinyl | 7 October 2004 | |
2nd Trim | 9 October 2004 | |
Pour Drives/Walks | 23 September 2004 | |
11 | Final Plumbing | 12 October 2004 |
Final HVAC | 12 October 2004 | |
Asphalt Drive | 7 October 2004 | |
Final Grade | 7 October 2004 | |
Gutters | 30 September 2004 | |
12 | Final Electric | 14 October 2004 |
Final CBus | 14 October 2004 | |
Drywall Punch | 15 October 2004 | |
Conductors | 12 October 2004 | |
13 | 2nd Roll | 19 October 2004 |
Mechanical Inspections | 20 October 2004 | |
Tractor Sod Grade | ||
Sod/Seed/Landscape | ||
14 | Carpet | 19 October 2004 |
Clean | ||
Final Paint | ||
Certificate of Occupancy | ||
Punchout | ||
QUALITY WALK | ||
15 | PreSettlement Inspections |